Formal payment claim under the Construction Contracts Act 2002 — the correct legal format for claiming progress payments in NZ.
How to use: Serve this payment claim in writing. The respondent has 20 working days to issue a payment schedule. All fields are editable — click any text to change it.
Click to upload logo
PAYMENT CLAIM
This is a payment claim served under the Construction Contracts Act 2002. The respondent must respond with a payment schedule within 20 working days of receiving this claim, or the claimed amount becomes payable in full.
Claimant (Contractor)
Your Business Name
Address
GST No: [your GST number]
Respondent (Principal / Client)
Client / Developer Name
Address
Construction Work / Services
Project name and site address
Claim Period
Work performed from [start date] to [end date]
| Description of Work | Scheduled Amount ($) | % Complete | Claimed ($) |
|---|---|---|---|
| Contract work — [description] | 100,000 | 60% | 60,000 |
| Approved Variation — VO-001 | 5,500 | 100% | 5,500 |
Gross amount claimed$65,500
Less retention (5%)($3,275)
Less previously claimed & paid($0)
Net claim (excl. GST)$62,225
GST (15%)$9,334
AMOUNT CLAIMED$71,559
Payment Instructions
Bank: [Bank Name] | Account: [XX-XXXX-XXXXXXX-XX] | Reference: CCA-001
Claimant signature / Date
Served on (respondent) / Date received